How to apply

Process Of Obtaining du Services

  • Developer to assign a consultant to apply for Design NOC and a Contractor to apply for construction and material NOC’s from du
  • Consultant or Contractor need to obtain the necessary NOCs [No Objection Certificate] by approaching du NOC department
  • After obtaining the NOC [design, construction and Material] and after completing 70% of the telecom systems, consultant or contractor can request for site inspection click here.
  • If du requirements [Telecom rooms, Customer premises setup and cable containment's] are snags free, du will take over the telecom rooms and provide the services after 30 working days from the handover date.
  • Properties should not be occupied prior to du services availability
  • du to inform the client upon service availability and accordingly client to notify tenants to approach du retails for service requests and activations